ISO 31000 Risk Management: A Global Guide to Risk Assessment
A useful ISO 31000 risk assessment starts with a decision. What are you trying to achieve? What could affect that objective? How much risk can the organisation accept, and who has the authority to decide?
This global guide follows a distributor’s delivery risk from initial assessment through treatment, verification and review. It includes a completed risk register, a practical explanation of the ISO 31000 principles and framework, and guidance on choosing related standards and assessment techniques. Official ISO 31000 overview
What ISO 31000 Risk Assessment Involves
ISO 31000 provides risk management guidelines for organisations of any size or sector. ISO describes risk as the effect of uncertainty on objectives. Begin with the outcome that matters, such as meeting a delivery commitment, maintaining a critical service or completing a project safely. Consider how uncertainty could affect that objective or create an opportunity. ISO 31000 guidelines · ISO 31073 risk management vocabulary
Before assessing a risk, define the scope, context and criteria. Agree which activities and time period the assessment covers, what information the team needs and which results require treatment or escalation.
| Risk assessment activity | Question to answer | What to record |
|---|---|---|
| Risk identification | What could happen, why and how could it affect the objective? | The source of uncertainty, the possible event and its consequences. |
| Risk analysis | How likely is the event, how serious could the effects be and how reliably do current controls work? | Evidence, assumptions, possible consequences and the limits of existing controls. |
| Risk evaluation | What does the analysis mean against our agreed criteria? | The decision to treat, retain, escalate or investigate the risk further. |
Risk treatment uses the assessment to select and implement a response. Communication, consultation, monitoring, review, recording and reporting support the process throughout. ISO/TC 262 overview of ISO 31000
Worked ISO 31000 Risk Assessment: A Distributor Depends on One Carrier
A distributor promises next-day delivery for priority orders on one route. Its main carrier missed two collections during the last comparable peak period. Dispatch received alerts and notified customers about the delays. With no approved backup carrier, it could not recover the missed collections.
The logistics manager and customer service team agreed on the decision: Can we rely on this route for priority orders during the next peak period?
Agree on the risk criteria before assigning a rating
The team assessed the likelihood of an unrecovered missed collection causing a late priority delivery. A backup carrier can make recovery more likely even if the main carrier’s performance stays the same.
| Criterion | Illustrative rules for this assessment |
|---|---|
| Likelihood | 1 — Unlikely: Recovery has been demonstrated under comparable peak conditions. 2 — Possible: A recovery arrangement has passed an initial test, but peak capacity remains uncertain. 3 — Likely: Recent collections were missed under comparable conditions, and there is no demonstrated recovery arrangement. |
| Consequence | 1 — Minor: The delay can be absorbed within the agreed delivery window. 2 — Moderate: A standard delivery commitment is missed. 3 — Serious: A priority order misses its agreed next-day window. |
| Evaluation | Multiply likelihood by consequence. 1–2 = Low. 3–4 = Medium. 6–9 = High. A high rating requires treatment or escalation before the route is relied on for priority orders. A medium rating requires an authorised decision and a review date. |
The scoring rules belong to this example. Choose criteria suited to your organisation’s objectives and evidence. ISO 31000 guidelines · IEC 31010 risk assessment techniques
Completed risk register entry
| Field | Illustrative record |
|---|---|
| Objective and scope | Meet next-day commitments for priority orders on the specified route during the next peak period. |
| Risk statement | If the main carrier misses a collection and dispatch cannot arrange an alternative in time, priority orders may miss the agreed delivery window. |
| Existing controls | Advance booking and missed-collection alerts. Dispatch logs show that alerts reached the team, which had no approved backup for the route. |
| Initial risk rating | High — 3 × 3 = 9. Two recent missed collections and the lack of a recovery arrangement support the likelihood rating. Missing a priority delivery meets the serious consequence criterion. |
| Treatment and owner | The logistics manager qualifies a backup carrier and arranges for dispatch to activate it when the primary carrier misses the agreed confirmation cut-off. |
| New risks to consider | Verify that the backup meets handling requirements, provides proof of delivery and operates within approved cost limits. |
| Verification result | In a test, dispatch booked the backup at the required notice. The vehicle collected on time, and proof of delivery confirmed that the shipment arrived within the required window. |
| Residual risk rating | Provisional High — 2 × 3 = 6. The test supports a lower likelihood of an unrecovered delay. Peak capacity remains unverified, and the consequence of a failed recovery is still serious. |
| Management decision | Keep the risk escalated and verify recovery under comparable peak conditions. If the follow-up supports likelihood 1, reassess the score to 1 × 3 = 3, Medium, and seek an authorised decision on whether to retain it. |
| Review owner and triggers | The logistics manager reports the result before the peak period. Reassess if backup capacity falls, the route changes or a recovery test fails. |
A risk owner monitors and escalates the exposure. A treatment owner carries out an assigned action. The organisation also defines who can accept residual risk, the risk that remains after treatment. In this case, the test improved the evidence, and the agreed criteria kept the risk escalated until the team could verify peak capacity. For related guidance on ownership, governance and oversight, see Veritas governance, risk and compliance information.
ISO 31000 Principles, Framework and Process
| Part | Purpose | Application to the distributor |
|---|---|---|
| Principles | Describe the qualities of effective risk management. | Involve the people who handle delays and use evidence from actual collections. |
| Framework | Integrates risk management into decisions and establishes responsibilities. | Define who can approve backup carrier costs and who can accept or escalate the remaining risk. |
| Process | Guides the assessment, treatment and review of a specific risk. | Assess route reliability, test the backup and review the rating before peak demand. |
The eight principles support the creation and protection of value. Each can influence how the organisation makes the decision. ISO/TC 262 overview of ISO 31000
| Principle | Practical application |
|---|---|
| Integrated | Include the risk review in the carrier approval decision. |
| Structured and comprehensive | Use consistent criteria and consider booking, collection, transport and recovery together. |
| Customised | Account for the different consequences of a priority-order delay and a standard delivery delay. |
| Inclusive | Ask dispatch, warehouse workers and customer service where the arrangement breaks down. |
| Dynamic | Reassess the risk when carrier capacity, routes or order volumes change. |
| Best available information | Use recent records and identify which operating conditions still need to be tested. |
| Human and cultural factors | Check whether dispatch staff can raise delays promptly and use the backup within their authority. |
| Continual improvement | Apply lessons from tests and actual disruptions to future decisions. |
How to Choose a Risk Assessment Technique
IEC 31010 provides guidance on selecting and applying assessment techniques. Choose a technique suited to the decision, the level of uncertainty and the information available. IEC 31010 risk assessment techniques
| Technique | When it helps | Example |
|---|---|---|
| Structured what-if discussion | Explore possible failures or changes before approving a plan. | Ask what happens if a carrier cancels after the final scheduled collection. |
| Likelihood and consequence matrix | Prioritise several risks using agreed criteria. | Compare supplier disruption, warehouse downtime and missed dispatch deadlines. |
| Bow-tie analysis | Identify controls intended to prevent an event and those that limit its consequences. | Review controls for loss of temperature control during shipment. |
| Scenario analysis | Explore what could happen when several conditions change together. | Consider high demand, staff shortages and reduced carrier capacity during the same week. |
If teams interpret terms such as likely or serious differently, agree on the criteria before comparing ratings. Record the evidence and assumptions that support the score. For a worked example of a matrix applied to workplace hazards, see the Veritas ISO 45001 hazard identification and risk assessment guide.
ISO 31000 Family: Which Document Supports Each Risk Decision?
| Published document | When to use it |
|---|---|
| ISO 31000:2018 — Risk management guidelines | Establish an organisation-wide approach to managing risk. ISO 31000 |
| IEC 31010:2019 — Risk assessment techniques | Select an assessment technique that fits the decision and available evidence. IEC 31010 |
| ISO 31073:2022 — Risk management vocabulary | Establish consistent terms for describing, evaluating and reporting risks. ISO 31073 |
| ISO 31022:2020 — Legal risk management | Assess and manage legal risk, such as uncertainty about contractual obligations. ISO/TC 262 catalogue |
| ISO 31030:2021 — Travel risk management | Assess risks associated with work travel and plan support for travellers. ISO 31030 |
| ISO 31031:2024 — Managing risk for youth and school trips | Consider supervision, transport, communication and emergencies on trips involving children or young people. ISO 31031 |
| ISO/TS 31050:2023 — Emerging risk and resilience | Assess emerging risks as evidence and conditions change. ISO/TS 31050 |
Publication status as of 28 November 2026. The ISO catalogue lists ISO/DIS 31000, ISO/WD 31011, ISO/AWI 31201 and ISO/AWI 31301 as projects under development. It lists ISO/TR 31004:2013 and IWA 31:2020 as withdrawn. Check the catalogue before relying on a draft or referencing an older publication. Official ISO/TC 262 catalogue
How ISO 31000 Supports Risk Assessment Across Other Standards
Organisations can use a shared approach to record evidence, assign risk owners and escalate decisions. Each discipline applies the requirements and criteria relevant to its work. ISO management system standards list · Veritas guide to integrated management systems
| Standard or group | Example risk decision |
|---|---|
| ISO 9001 — Quality management | Could reliance on one supplier affect product conformity or delivery commitments? |
| ISO 14001 — Environmental management | What environmental aspects and impacts arise from a process change, and what compliance obligations apply? |
| ISO 45001 — Occupational health and safety | Who could be exposed to moving vehicles, and how reliably do controls work across shifts? Veritas occupational health and safety risk assessment guide |
| ISO/IEC 27001 and ISO/IEC 27005 — Information security | What could result from unauthorised access to customer records, and how will the organisation treat that risk? ISO/IEC 27005 |
| ISO 22301 — Business continuity | What might disrupt dispatch, and which activities need to recover first based on the impact of disruption? |
| ISO 22000 — Food safety | Which hazards at a processing step need control, and how will those controls work in practice? |
| ISO 37001 — Anti-bribery management | What bribery exposure could arise from appointing an intermediary for public-sector work? ISO 37001 |
| ISO/IEC 42001 and ISO/IEC 42005 — AI management and impact assessment | How could an AI system’s recommendations affect individuals or groups, and what safeguards are appropriate? ISO/IEC 42005 |
| ISO 12100 — Machinery safety | What risks arise during operation, cleaning or maintenance, and how can the design reduce them? ISO 12100 |
| ISO 14971 and ISO 22367 — Medical device and laboratory risk | What harm could result from an incorrect device reading or a laboratory specimen identification error? ISO 14971 · ISO 22367 |
Worked example — One equipment change, three assessments. A manufacturer installs an automated packing line. The quality team assesses packaging accuracy. The environmental team examines changes to waste and energy use. The safety team evaluates worker exposure during operation, cleaning and maintenance. Management tracks owners and actions in one register. Each team retains the criteria, evidence and approvals relevant to its decision. For more sector examples, see Veritas’s guide to ISO standards by industry.
Can an Organisation Be Certified to ISO 31000?
ISO 31000 is a guidance standard. ISO states that it cannot be used for certification purposes. Organisations can use it for training, internal reviews and evaluating risk management practices. A course completion certificate describes an individual’s course outcome. An organisational review documents findings against an agreed scope. Official ISO 31000 overview
Veritas Assurance Information by Country
Use the relevant country page for general Veritas Assurance enquiries and information about management system standards. For an ISO 31000 training enquiry, identify the countries where your team operates, the roles involved and the risk management skills the team needs to develop.
| Region | Veritas Assurance country pages |
|---|---|
| Gulf countries | United Arab Emirates · Saudi Arabia · Qatar · Bahrain · Kuwait · Oman |
| Other Middle Eastern countries | Iraq · Jordan · Lebanon |
| North Africa | Egypt · Morocco · Tunisia |
| Asia | India · Malaysia · Singapore · Philippines |
| Europe | United Kingdom |
| North America | United States · Canada |
Discuss ISO 31000 Training With Veritas Assurance
Tell us which decisions your team needs to support, which roles are involved and where staff need more practice with assessment, treatment or review. Foundation training introduces the principles and process. Auditor training focuses on reviewing risk management arrangements and evaluating evidence within a defined scope. Veritas ISO 31000 Foundation training · Veritas ISO 31000 Auditor training
Enquire About ISO 31000 Training
Disclaimer. This global guide is for information and awareness. The risk register, criteria, scores and examples are illustrative. Refer to the official publications and apply criteria appropriate to your organisation, obligations and decisions.
Frequently Asked Questions
How do we write a risk statement that leads to a decision?
What if two departments give the same risk different ratings?
How should we rate a risk when evidence is limited?
Why can likelihood fall while the consequence rating stays the same?
Can a treatment be complete while the remaining risk still needs to be escalated?
Who can accept residual risk?
What should trigger a review before the scheduled date?
Can several ISO management systems use one risk register?
Discuss ISO 31000 Training With Veritas Assurance
Tell us which risk decisions your team handles and which skills you want to develop so we can discuss relevant training options.